Mapleleaf project may be finished this week
Construction work on Mapleleaf could be finalized as early as this week, according to engineers from Warner Engineering.
The remainder of the concrete on the Mapleleaf Drive project was poured Monday afternoon and Kinney?s has started finishing the final backfill and grading.
Enright Seeding is slated to finish the seeding Wednesday afternoon, weather permitting.
Jones Contracting, tentatively, is hoping to get ...
N/A
Sep. 30, 2018 9:51 pm
Construction work on Mapleleaf could be finalized as early as this week, according to engineers from Warner Engineering.
The remainder of the concrete on the Mapleleaf Drive project was poured Monday afternoon and Kinney?s has started finishing the final backfill and grading.
Enright Seeding is slated to finish the seeding Wednesday afternoon, weather permitting.
Jones Contracting, tentatively, is hoping to get the striping company to complete the striping and remove traffic control devices on Friday, Oct. 14.