Road construction south of New London began this week
Construction will continue for two weeks
May. 5, 2025 12:57 pm, Updated: May. 5, 2025 1:12 pm
Southeast Iowa Union offers audio versions of articles using Instaread. Some words may be mispronounced.
The Henry County Engineer’s Office has announced a road construction project near the 305th Street and Quincy Avenue intersection beginning Monday, May 5.
The project will consist of several crossroad pipe replacements and the intersection being reconstructed to a “T” intersection. The work will take approximately two weeks, weather permitting.
There will be daily road closures depending on the location of the crossroad pipe that is being replaced. The roads will be open each night. Please pay attention to signs for location closure.
Construction updates and questions can be answered at 319-385-0762.